Extension to Montessori elementary school
Mataréstraße

Extension with multifunctional canteen and OGS areas

Current: Construction decision made, planning award procedure begins

In the project phase timeline, this project is in the construction planning phase.
The street perspective shows the wooden façade of the extension.


Occasion and goal

The increasing demand for OGS at this location can no longer be met in the existing building. A multifunctional extension with canteen and OGS areas is intended to cover the demand.

  • Key data

    • Canteen for 280 meals
    • Dining room as multi-purpose room
    • 2 OGS group rooms, team room, meeting room, management office, ancillary rooms
    • Net room area ground floor + upper floor: 687 m² (400 m² ground floor + 287 m² upper floor)
    • Gross volume ground floor + upper floor: 3,590 m³
    • Start of implementation: 1st quarter 2026
    • Expected completion date: December 2027
    • Timber construction
    • District heating and PV system
    • Extendable
    • Roof greening and façade trees
    • Architects after successful tender: Herkrath und Herkrath Architekten

Building placement and urban integration

The new building to be erected is positioned in the gap between the gymnasium and the residential development on Zeppelinstraße adjacent to the school site. It takes up the height of the street frontage of the gymnasium and continues it. Some distance is still kept to the residential buildings. The new building also takes up the staggered heights of the gymnasium towards the schoolyard and blends into the ensemble.

Site plan of existing and extension building


Room program and utilization concept

The canteen will be located on the first floor. The dining hall will open up to the schoolyard with large windows and can also be used as a multi-purpose room. The new group rooms as well as the OGS team and administration rooms will be located on the upper floor. There will be no corridor. The rooms will be accessed via a multi-purpose/cluster room. Each floor will of course have the necessary sanitary facilities and ancillary rooms.

The building can be accessed independently of the rest of the school building. It is barrier-free thanks to the planned elevator, among other things.


Further project information

  • Building construction and materials

    The building is to be constructed in timber for reasons of sustainability. Emphasis is placed on renewable and reusable materials.

    The wood will be visible in the façade as well as in the ceiling beams, partly in the interior walls and also in the suspended ceiling in the dining room. The floors in the common rooms will be made of linoleum. The group rooms will have light-colored acoustic ceilings. The overall aim is to create a bright, natural and friendly atmosphere.

  • Technical equipment and energy supply

    The entire roof of the building will be covered with a PV system in order to contribute to climate neutrality. To generate heat, the new building will be connected to the school's existing heating system in an interim phase. In the future, the entire school building will be connected to the planned district heating system.

    With the exception of the dining room, the glazing is fitted with external blinds as sun protection. As the dining room will have many French windows, fixed sun protection in the form of vertical wooden slats will be used here in some cases. The common rooms will have decentralized ventilation units with heat recovery.

  • Greening concept

    The roof of the building will be greened. Façade trees will be planted in front of two façades. The emergency staircase will also be planted with greenery.

  • Future viability and flexibility

    For future developments, the possibility of adding a further storey has been taken into account in the planning and dimensioning up to service phase 3.

  • Reorganization and linking of existing buildings

    By adding and removing non-load-bearing walls, the school will have a total of 12 classrooms, 3 multi-purpose rooms, 3 specialist rooms, 6 differentiation rooms, staff rooms, administration, janitor's office, checkrooms and ancillary rooms in the old building and pavilion once the project is complete. The janitor's office will be relocated from the basement to the first floor, the teachers' room and administration will be spatially linked and existing passageways will be removed. There are still 4 OGS group rooms in the pavilion.

  • Sustainability aspects

    Sustainability is playing an increasingly important role in the City of Aachen's construction projects. The exemplary function as a public building owner, the desire for healthy buildings and economical and ecological operation over the entire service life lead to requirements that go far beyond those of an energy-efficient building.
    Planning should therefore be based on the following assessment criteria:

    • Ecological quality
    • Economic quality
    • Socio-cultural quality
    • Technical quality
    • Process quality
    • Location features

    The extension is responsibly aligned with the principles of future construction.

  • Drawings

    First floor plan
    First floor plan
    First floor plan
    First floor plan
    Cut
    Cut
    Courtyard view
    Courtyard view
    Street view
    Street view
    Side view
    Side view
    Window connections in detail
    Window connections in detail
    Site plan
    Site plan




  • Political mission

    In the Committee for Schools and Further Education on 28.10.2021, the administration was commissioned to update service phases 1 to 3 for the Mataréstraße Montessori elementary school in accordance with HOAI, including cost calculation for variant 1.

Help with accessibility

  • General

    We make every effort to ensure that our websites are accessible. You can find details on this in our accessibility statement. You can send us suggestions for improvement using our"Report a barrier" feedback form.

  • Font size

    To adjust the font size, please use the following key combinations:

    Larger

    Ctrl
    +

    Smaller

    Ctrl
  • Keyboard navigation

    Use TAB and SHIFT + TAB to navigate through next/previous links, form elements and buttons.

    Use ENTER to open links and interact with elements.