Conversion of Inda-Gymnasium from G8 to G9

Extension building


In the time bar of the project phases, this project is in the construction phase.
Rendering view


Occasion and goal

On the basis of the 13th School Law Amendment Act passed by the NRW state parliament on July 11, 2018, the duration of the educational courses at secondary level I was revised. All eight municipal grammar schools in Aachen have decided to switch to nine years (G9). By the 2026/2027 school year, all year groups will once again be taught according to the new curricula.

  • Key data

    • Two-storey extension
    • Implementation during ongoing operations
    • 6 classrooms, 2 multifunctional rooms
    • 4 adjoining rooms
    • PV system
    • Heat supply: planned geothermal energy
    • Climate-neutral operation
    • increased Aachen standard
    • Start: February 2024


Construction site photos

Architectural concept

  • Two-storey extension with partial basement on building wing 2
  • Architecture and design language based on the existing building with a colorful accent
  • Room program: 6 classrooms, 2 multifunctional rooms, 2 teaching materials rooms, building services room, storage room
  • Glazed connecting element for barrier-free access to the new building and building tracts 1 and 2 with an elevator
  • Consideration of a PV system on the new roof area, partial roof areas with a green roof
  • Redesign of outdoor facilities with replacement planting

Site plan of the extension including open space planning.

Energy concept

  • Compact design
  • Structural thermal insulation in accordance with the increased Aachen standard
  • Installation of a PV system on the roof, climate neutrality in operation
  • Planned conversion of the heat supply to geothermal energy

Further project information

  • Basic data inventory

    The Inda-Gymnasium includes the multi-winged main building from 1973, a science extension from 2007 and a sports hall. Around 1,350 pupils attend the 5-form grammar school.

  • Building concept

    The planned extension will be built between building wing 2 and the sports hall at Romerich.

    In order to be able to carry out the work while the school is open, four classes have to be moved out of wing 2 of the building

  • Floor plans

    First floor plan of the extension
    First floor plan of the extension
    Floor plan of the upper floor of the extension
    Floor plan of the upper floor of the extension
    Basement floor plan of the extension
    Basement floor plan of the extension

Help with accessibility

  • General

    We make every effort to ensure that our websites are accessible. You can find details on this in our accessibility statement. You can send us suggestions for improvement using our"Report a barrier" feedback form.

  • Font size

    To adjust the font size, please use the following key combinations:

    Larger

    Ctrl
    +

    Smaller

    Ctrl
  • Keyboard navigation

    Use TAB and SHIFT + TAB to navigate through next/previous links, form elements and buttons.

    Use ENTER to open links and interact with elements.