Brief info
- Project: Land use plan amendment (FNP) and development plan no. 970 - Roermonder Straße / Amstelbach -
- Location: Aachen-Richterich district in the area between the Roder Weg industrial estate, Amstelbach and Roermonder Strasse
- Size: FNP procedural area approx. 0.7 ha; B-Plan planning area: approx. 4.85 ha (This also includes the areas of the old Roermonder Straße and the Roermonder Straße Kohlscheider Straße junction. In the further concretization of all plans, the plan area will probably be reduced in size).
- Planned use: FNP: Area for public use, BPlan: Area for the fire department, area for a recycling center, development facilities (part of the planned "main development bypass").
- Project phase: early participation
Map
Process status
The planning committee passed the following resolution on April 26, 2018:
The planning committee takes note of the administration's report and instructs the administration to draw up a development plan for the construction project - Roermonder Strasse / Amstelbach. It also instructs the administration to amend the 1980 land use plan accordingly.
It resolves to carry out public participation in the urban land-use planning in accordance with Section 3 (1) BauGB and the Council's guidelines in sections III, 1 and 2.
The planning, including a presentation of the expected effects, will be on display for public inspection in the foyer of the Aachen-Richterich district office, Roermonder Straße 559, from Monday to Friday from 8:00 a.m. to 12:00 p.m., and on Wednesdays from 2:00 p.m. to 5:30 p.m., from 4 June 2018 to 29 June 2018. The public hearing for citizens will take place on Tuesday, June 5, 2018 from 7 p.m. to 8 p.m. in the meeting room at Schloss Schönau, Schönauer Straße 20.
Explanations on planning
The aim of the planning is to build a new equipment depot for the Aachen-Richterich volunteer fire department, a recycling center for the northern area of Aachen and the necessary development (part of the "main development bypass"). In the 1980 land use plan, it is necessary to change the existing zoning from agricultural land to land for public use.
The existing plans for the fire department and the main development have been expanded to include planning for the recycling center, so that an overall view of the area can be taken. A section of the planned Aachen-Herzogenrath high-speed cycle path is also located within the planning area.
Note on the provision of information on the Internet
In accordance with Section 4a (4) BauGB, the possibilities offered by electronic information technology are hereby additionally utilized by publication on the Internet.
Download
Contact us
Development plan:
Land use plan: