- Project: Development plan no. 914 - Eupener Straße / I. Rote-Haag-Weg - procedure in accordance with Section 13a BauGB
- Location: in the district of Aachen-Mitte for the area between Eupener Straße, Heidweg, Waldstadion and I. Rote-Haag-Weg
Current
The documents relating to the preliminary draft were available for public inspection in the foyer of the administration building at Marschiertor from 22.03.2010 to 06.04.2010.
Process status
At its meeting on June 1, 2006, the city's planning committee decided to draw up the development plan for the above-mentioned plan area using the accelerated procedure as a development plan for internal development in accordance with Section 13a (1) sentence 2 no. 1 BauGB without carrying out an environmental assessment in accordance with Section 2 (4) BauGB.
The public information process is currently underway.
Explanation
In 2005, a framework concept for an orderly and urbanistically desirable residential development in Aachen's southern district formulated fundamental urban and natural criteria for the preservation and partial densification of individual settlement areas.
The southern district was also examined to determine how urgently the use of planning law instruments is required in the individual settlement areas. On the basis of this investigation, the decision was made to draw up a plan for the Eupener Straße / I. Rote-Haag-Weg area.
The following urban development goals are to be achieved:
- Safeguarding the orderly urban structure and the existing character
- Securing the villa-like development on spacious plots of land
- Safeguarding the existing characteristic greenery
- Moderate control of further structural development
Internet
In accordance with Section 4a (4) BauGB, the possibilities of electronic information technology are hereby utilized in addition by publication on the Internet. The representations on the Internet are non-binding. Only the original plans and original documents in the public display are legally binding.